Keeping mining downtime short: TAKRAF combines 3D measurement, laser cladding and pre-assembly in gearbox overhaul

TAKRAF combined advance planning, 3D housing measurement, laser cladding and pre-assembly to keep the overhaul of an 82-ton gearbox from LEAG's Nochten mine short; the test run was reached in six weeks.

82-ton TAKRAF bucket-wheel gearbox at the Lauchhammer Product & Service Center
Image: TAKRAF Group
Contents
  1. Planning started before the unit arrived
  2. Measurement, restoration and preventive replacement
  3. Load testing and return to site

For heavy mining equipment, drivetrain maintenance is often a question of how long the machine stands still. A service project published by TAKRAF Group on 26 November 2026 shows how an overhaul was organised to keep that time short: an 82-ton gearbox that ran for 11 years at LEAG’s Nochten open-cast mine in Germany was restored at Lauchhammer using advance planning, 3D measurement and laser cladding, with the test run reached after just six weeks.

Planning started before the unit arrived

Because excavator downtime was a key consideration for the customer, all activities were coordinated to keep the maintenance period as short as possible, TAKRAF says. Planning began before the gearbox reached the Lauchhammer Product & Service Center: new internal components were pre-assembled and the gear stages completed, which the company says substantially reduced the time needed for final reassembly.

The unit is a bucket-wheel gearbox built at Lauchhammer in 2015 that transfers the power of two 1,250 kW motors to the bucket wheel of an SRs 6300 excavator.

Measurement, restoration and preventive replacement

Inspection after dismantling showed the components in good condition after more than ten years in the mine, yet the gears and rolling bearings were swapped out as a preventive step for the rest of the unit’s service life. A 3D survey of the three-section housing concentrated on the bearing seats; where needed, worn or damaged zones were laser-clad and then machined to bring dimensions and fits back to specification.

Load testing and return to site

After reassembly, the gearbox was tested at the facility; TAKRAF notes that large gearboxes overhauled at the center are tested under load before leaving. The unit left for Nochten on a heavy transport in early November.

According to the company, service activities account for more than half of the orders handled at Lauchhammer, which supports customers with inspection, maintenance, refurbishment, replacement parts and overhaul work alongside new equipment supply.

Sources

  • TAKRAF Group, “TAKRAF Group Expertise Extends Equipment Life: 82-ton Bucket-Wheel Gearbox Overhauled in Lauchhammer”, 26.11.2026 — takraf.com

Image: TAKRAF Group

Editör

Author

Türkiye endüstrisine, alana özel, spesifik yayınlar üreten MONETA Tanıtım’ın sektörel dergilerinin editörlüğünü yapmaktayım. Yeni nesil, dinamik yayıncılık anlayışıyla, dijital ve basılı mecralarda içerik geliştirmek için çalışmaktayız.

Sponsored

Leave a Reply

Your email address will not be published. Required fields are marked *